Late Tuesday roof update
The gutter issue has been partially resolved, and work can continue. The gutters will be replaced over units 4326 & 4327 on Wednesday.
Thursday, 7 am, the plan is to continue with roofing on the North end of building 3. This will involve tear off and will be very loud, smelly, and messy. It will also be a long day, as they will work until the roof is drytight. Friday they can do finishing work, even though there is a chance of rain.
Building 3 is doing a great job of keeping the cars clear, so keep up the good work!
Thanks to everyone for your patience as this project rolls on.

Comments are closed.